Over and under billing, explained with one job
Over and under billing compare two things: what you have invoiced on a job, and what you have earned by doing the work. This page walks through one job, line by line. The job is made up. It comes from a sample pack on made-up numbers, not from any real company.
The job
Job 2531, a lab power expansion. Here is what the office knows at the end of the month:
- Original contract: $1,180,000
- Approved change orders: $64,000
- So the contract amount is $1,244,000
- Estimated total cost, updated this month: $1,030,000
- Cost to date, from QuickBooks: $964,480
- Billed to date, from the invoices: $1,012,000
Step 1: how complete is it?
Percent complete = cost to date ÷ estimated total cost
$964,480 ÷ $1,030,000 = 93.6%
The job has used 93.6% of the cost it is expected to take, so it counts as 93.6% done.
Step 2: what has it earned?
Earned revenue = percent complete × contract amount
93.6% × $1,244,000 = $1,164,867
That's the share of the contract the work so far has earned.
Step 3: billed ahead, or behind?
Over or under billing = billed to date − earned revenue
$1,012,000 − $1,164,867 = −$152,867
The number is negative, so the job is under billed by $152,867. The company has done $152,867 more work than it has invoiced.
What that means
- It's cash you have earned and not asked for. The job is nearly done. If the last invoices don't catch up, that money can be hard to collect once the crew has left.
- It may also mean the estimate is off. If cost to date is running ahead because the job is over budget, percent complete looks higher than the real progress. Check the estimate before you send a bigger invoice.
- Either way it's worth a look this month, not at year end.
The other direction
Another job in the same sample, a warehouse lighting retrofit:
- Contract amount: $504,500
- Estimated total cost: $412,000
- Cost to date: $389,750, so 94.6% complete
- Earned revenue: $477,255
- Billed to date: $488,000
- Over or under: $488,000 − $477,255 = $10,745 over billed
Over billing means the company has invoiced $10,745 more than the work so far has earned. It's not wrong in itself: front-loaded billing is common on some jobs. But the money is owed back in work, and a large total of over billings across many jobs can hide a cash squeeze later.
Why the total matters
On a work-in-progress schedule, every open job gets this treatment, and the over and under billings are added up. The totals are what your CPA and bonding agent ask to see: a company that is steadily under billed is waiting on its own cash, and one that is steadily over billed may be spending money for work it hasn't done yet.
How to build the whole schedule from your own books is on the page How to build a work-in-progress schedule from QuickBooks Online.
Want a plain answer on your own books?
Email one QuickBooks export and get a plain answer, usually within one business day: can your books support a work-in-progress schedule, and what is missing. Free. No fees, and nothing to buy. How to send it, and the terms, are on the free check page.
The full sample pack these two jobs come from, on made-up numbers: PDF and Excel.
Luke Lin, San Jose. I'm not a CPA, and this page isn't tax or legal advice.