How to build a work-in-progress schedule from QuickBooks Online

A work-in-progress schedule shows, for every open job, how much of the work is done, how much you have earned, and whether your billing is ahead of the work or behind it. It's the kind of schedule your CPA and bonding agent ask to see, and it's most useful when you keep your own every month, not only at year end.

QuickBooks Online holds about half of what you need. This page shows which half, what you add yourself, and how to put it together.

What goes on the schedule

One row per open job, with these columns:

  1. Contract amount: the original contract plus approved change orders.
  2. Estimated total cost: what you now expect the whole job to cost.
  3. Cost to date: what the job has cost so far.
  4. Percent complete: cost to date divided by estimated total cost.
  5. Earned revenue: percent complete times the contract amount.
  6. Billed to date: what you have invoiced on the job.
  7. Over or under billing: billed to date minus earned revenue. A positive number means you have billed ahead of the work. A negative number means you have earned more than you have billed.

This way of measuring progress, by cost, is the most common one for contractors. If your CPA uses a different one for your year-end schedule, use theirs.

What QuickBooks Online holds

What it does not hold

Some higher QuickBooks Online plans now include a basic work-in-progress report. Retention, overhead and some year-end adjustments still end up in a spreadsheet (James Moore).

First: make sure costs land on jobs

The schedule is only as good as your cost to date, and cost to date only works if each cost is assigned to a job.

Building it, step by step

  1. Run the cost report. Go to Reports, search for "Profit and Loss by Customer", and set Report period to All Dates and Accounting method to Accrual.
  2. Export it to Excel. It gives cost to date and income for every customer or project.
  3. Check the total. Add up cost to date across all jobs and compare it with your job cost accounts on the regular Profit and Loss for the same dates. If the job total is smaller, the difference is cost that isn't on any job yet. Fix that first.
  4. Add your three numbers per job in new columns: contract amount with approved change orders, estimated total cost, and billed to date from your invoices.
  5. Work out the rest:
    • Percent complete = cost to date ÷ estimated total cost
    • Earned revenue = percent complete × contract amount
    • Over or under billing = billed to date − earned revenue
  6. Read the bottom line. Large under billings are money you have earned and not invoiced. Large over billings are money you have collected for work not yet done.

A worked example with one job is on the page Over and under billing, explained with one job.

Three things that throw the schedule off

Want a plain answer on your own books?

Email one QuickBooks export and get a plain answer, usually within one business day: can your books support a work-in-progress schedule, and what is missing. Free. No fees, and nothing to buy. How to send it, and the terms, are on the free check page.

To see what a finished schedule looks like first, there's a sample pack on made-up numbers: PDF and Excel.

Luke Lin, San Jose. I'm not a CPA, and this page isn't tax or legal advice.

Back to the home page